|
The former Christ Church building and the neighbouring Scout Hut were vacated at
the beginning of September 2006.
Our Not at home plans were put into operation so that the church and
uniformed organisations could continue all their activities in temporary venues.
For the next few months the buildings stood empty as most of the work took
place behind the scenes. There was no visible progress on the site as contracts
were negotiated and surveying and other preparatory work completed.
The building contract was awarded to
Mansell Construction Services Ltd, and
they took over the site in March 2007.
During April, Central Networks disconnected the electricity substation
and installed a new one on the other side of the site.
The former Christ Church building was demolished on 3 May, followed by the
Scout Hut over the next few days. This milestone event can be viewed here in a brief
video
or as a sequence of
photos.
Once the site had been cleared, the side access road was constructed. After
laying the foundations, the builders erected the steel framework of the new building.
Heavy rain during July delayed progress briefly, but work soon continued as the
construction of the walls and roof got under way.
The Bishop of Birmingham, David Urquhart, laid the foundation stone on
14 September. The foundation stone of the old building was installed alongside
the new one, as a sign of continuity from one building to another.
By mid November the roof was complete, which allowed the external scaffolding to
be removed. Most of the external windows and doors were also installed, giving the
building (from the outside, at least) much more of the appearance of the finished
article.
In December we were invited on to the site to look around the interior
of the building. Church members and their families joined with the builders
to sing Christmas carols and enjoy some food and drink - a generous gesture
by Mansells.
The heating system was also commissioned during December. Underfloor
heating has been installed, so that the walls in the main halls are completely
clear of radiators.
Formal handover took place on Friday 22 February 2008, and our equipment was moved
into the building over the following weekend ready for the first service on
Sunday 2 March.
|